Perspective Nexus Construction Update June 2024


We are thrilled to share the latest updates from our Perspective Nexus development. With construction moving at a rapid pace and sales going exceptionally well, there's never been a better time to secure your dream home in Palm Beach. But hurry, with only 9 homes remaining, these residences are selling fast!

Construction Snapshot

Our construction team, led by the talented LPS Group, is making incredible and faster than anticipated progress. With sunny days all week, LPS Group are powering along schedule. We have great confidence in their ability to deliver outstanding results on schedule for Q3, 2025!

Hear From The Builders…

Here's a snapshot of milestones onsite:

Pile Installation and Trimming: Completion of the basement retaining walls, with 354 piles already installed.

Capping Beam Works:  The capping beam works were completed, creating a giant retaining wall around the site's perimeter. In early June, LPS Group installed temporary propping of the capping beam, bracing the retaining walls to support the perimeter during excavation. This allows start for the excavation for the basement.

Bulk Excavation: Initial bulk excavation for the basement is set to begin soon, marking another major milestone in our construction timeline. 

Temporary props for the capping beam.

Piles installed around the perimeter of the site, with concrete capping beam on top.

With the Gold Coast sun shining, LPS Group are doing a stellar job, ensuring that the project is on track for Q3, 2025.

Key Activities For June 2024…

  • Bulk Excavation: Digging a large hole is currently underway.

  • Shotcrete Blinder Works: Spraying concrete on the basement walls will begin following the excavation down.

  • Dewatering Set-Up: Initial steps for dewatering have started.

  • Basement Blinder Slab: A thin bottom layer will be poured by the end of June to allow the builder to start constructing the basement slab.

 

Selling Fast: Only 9 Residences Remaining! 

Since the start of construction, we've seen a surge in sales activity. We are excited to announce that 26 residences are now under contract, leaving only 9 residences remaining.

We extend a warm welcome to all our new buyers and are delighted to have you join the Sherpa family. Our Sherpa Team will contact you in the coming weeks regarding customisation options, to create your dream apartment.

Secure your slice in paradise…

Call 1300 327 299 to secure your dream home in Palm Beach….

With construction running better than ever, stay tuned for our upcoming updates of Perspective Nexus!

Next
Next

SHERPA CLIMBS HIGHER: Three New Palm Beach Sites Acquired